Phase 2 Saba solar park project well on its way to completion
Construction of phase 2 of Saba Electric Company (SEC) solar park projects next to the Juancho Yrausquin Airport is progressing as planned. The frames with the 2,960 solar panels should be in place in the third week of December. Once the second solar park is operational in the first quarter of 2019, the two solar … Continue reading Phase 2 Saba solar park project well on its way to completion