Road works for installation of fiber optic cable, March 27 – April 26

During the upcoming weeks there will be construction to some meter walls and fiber optics cable is to be installed by SEC and HES Con throughout the island’s road infrastructure. The predicted dates for this work are as follow:

Meter wall construction to be performed commencing March 13th, 2017 in the areas of:

  • Mountain Road Entrance
  • SEC Warehouse St. Johns
  • The Bottom

Fiber Optics Cable Installation:

  • Carl Hassell’s Residence to Airport March 27 — 30
  • Chad Hassell’s Residence to Carl Hassell’s Residence March 31 — April 3
  • Chad Hassell’s Residence to Mountain Road April 4 — 5
  • Mountain Road to Tourist Office April 6 — 7
  • Tourist Office to SEC Warehouse April 10 — 12
  • SEC Warehouse to SEC Office April 13 — 20
  • SEC office to Power Plant Aril 21 — 26

Above dates are subject to change due to unforeseen circumstances. The public is advised to exercise caution within the working areas. We apologize for any inconvenience this may cause.

The Executive Council of the Public Entity Saba,